What Are the Requirements for Damp-Proof Membranes in Floors and Walls?

Quick Answer: A damp-proof membrane (DPM) in a ground floor slab must be at least 1200 gauge (300 micron) polythene, continuous, lapped and taped at joints, with a minimum 150mm upstand at all edges linking to the wall DPC. Approved Document C requires a DPM in all new ground-bearing concrete floors. For walls, the damp-proof course (DPC) must be a minimum 150mm above external ground level and must be a continuous horizontal barrier of impermeable material to BS 6515 or BS 743.

Summary

Damp-proof membranes and damp-proof courses are foundational requirements in UK building construction. They prevent ground moisture from rising through capillary action into floors and walls, which would otherwise lead to structural damage, finishes failure, and health issues associated with damp living conditions. Despite being a well-established requirement, failures in DPC and DPM installation or specification are among the most common defects found in surveys of UK housing.

The terminology is sometimes confused. A damp-proof course (DPC) is a horizontal (or occasionally vertical) barrier in a wall. A damp-proof membrane (DPM) is a continuous sheet installed under or within a floor slab. Both serve the same fundamental purpose — breaking the capillary path between ground moisture and the building fabric — but they are different products with different installation requirements.

In new build, requirements are set out primarily in Approved Document C (Site preparation and resistance to contaminants and moisture) of the Building Regulations. Approved Document C also covers radon protection, which overlaps significantly with DPM specification and in some parts of the UK must be combined with the DPM.

Key Facts

Quick Reference Table

Spending too long on quotes? squote turns a 2-minute voice recording into a professional quote.

Try squote free →
Application Minimum Specification Key Detail Regulation Reference
Ground floor DPM (below slab) 1200 gauge (300 µm) polythene Lap joints min 150mm, tape; 150mm upstand to wall Approved Document C, Section 4
Ground floor DPM (above slab) 1200 gauge polythene or proprietary Protect from screed aggregate puncture; lap and tape Approved Document C
Radon area DPM 300 µm polyethylene, all joints taped, 300mm lap Link to radon sumps or ventilation layer if required BRE BR 211
Wall DPC (horizontal) Min 150mm above external ground; BS 6515 or BS 743 Continuous; cavity wall must be bridged by tray DPC Approved Document C
Cavity tray DPC Lead, bitumen, or proprietary tray Extends to outer face with weep holes at 900mm centres NHBC Chapter 6.1
Bridging DPC/DPM at junction Polythene strip or proprietary membrane tape Links wall DPC level to floor DPM level Approved Document C

Detailed Guidance

Ground Floor DPM Installation

The DPM is typically laid after the hardcore and blinding are compacted and levelled, before or after the slab pour depending on the specified position.

Below-slab DPM (oversite) This is the simplest and most common position. The DPM is laid on clean sharp sand blinding (minimum 25mm) over compacted hardcore. The polythene sheet is lapped at joints by a minimum 150mm and taped with a compatible tape. At all edges, the DPM is turned up the wall face and secured temporarily before the slab is poured. The slab covers the DPM completely.

Puncture during the pour is a risk. Avoid dragging reinforcement mesh across the membrane. Where thermal insulation is being incorporated at slab level (below the slab is unusual, but possible in some passive construction types), the insulation boards are typically placed on top of the DPM, with the slab poured over the insulation.

Above-slab DPM (sandwich) The slab is poured first, then the DPM is placed on the slab surface before the screed. This approach keeps the slab within the thermal envelope (useful for thermal mass), but requires the DPM to be protected from puncture by the screed aggregate — typically by placing a 50mm sand layer over the DPM before screeding.

The 150mm upstand must still be achieved; the DPM must be turned up at all edges and linked to the wall DPC. With an above-slab DPM, this linking junction can be awkward to detail, particularly at the inner face of a cavity wall.

Wall DPC Requirements

A horizontal DPC in a cavity wall must be positioned at two levels:

  1. In the inner leaf — at or just above floor level, continuous across the full leaf width, minimum 150mm above external ground
  2. In the outer leaf — at the same or slightly lower level, continuous across the full outer leaf width

Both must be continuous. The cavity tray bridges the cavity between the two leaves at window and door openings and at any level change between inner and outer leaves. At lintels, a combined lintel with integral DPC tray is standard (Catnic, IG, Teplo). At the base of the wall, the cavity tray sits above the cavity insulation with weep holes at 900mm centres on the outer leaf to allow any water collecting on the tray to discharge.

DPC materials include polythene (most common in new build, lightweight, easy to join), bituminous felt (traditional, still used in conservation and repair work), lead (used historically; still appropriate in conservation areas where lead flashings are maintained), and engineering brick (two courses as a physical DPC — used in traditional solid-wall construction).

Linking DPC and DPM

The connection between the wall DPC and the floor DPM is critical and is frequently poorly detailed on site. The intent is to create a continuous impermeable barrier from the base of the wall DPC down through the junction and across the floor. If the junction is not properly sealed, ground moisture can enter at the skirting/floor interface and rise up the internal wall plaster.

The standard approach for a cavity wall with a below-slab DPM:

Where the DPC and DPM are on very different levels (for example, a new DPM in an existing building with a historic DPC at a higher level), a vertical DPM strip bridges the gap — essentially a strip of DPM material fixed vertically on the wall face, bonded to the DPC above and the horizontal DPM below.

Radon DPM Requirements

In England and Wales, the radon potential map (BRE/PHE indicative atlas) identifies high, medium, and low radon risk areas. In areas of high radon potential (above 3% of homes expected to exceed the Action Level of 200 Bq/m³), full radon-protective measures are required by Building Regulations Part C. In medium-risk areas, basic radon protection (enhanced DPM plus provision for a future sump) is required.

A radon DPM is a 300 micron polyethylene sheet, typically Visqueen Gas Membrane or equivalent, with all joints lapped a minimum 300mm and taped with compatible tape. The key distinction from a standard DPM is that the continuity and sealing requirements are more stringent — every penetration (pipes, cables) must be sleeved and sealed.

In the highest-risk areas, a radon sump is provided below the slab, ventilated naturally or by a fan to depressurise the subfloor zone. The DPM forms the lid of this depressurised zone and must be perfectly sealed. Radon membranes must also be resistant to gas permeation — standard polythene is acceptable at 300 micron; thicker or proprietary cross-laminated membranes offer enhanced protection.

Diagnosing Failed or Missing DPC/DPM

In existing buildings, the absence or failure of a DPC is a common finding in surveys. Diagnostic signs include:

Note that these signs can be mimicked by penetrating damp and hygroscopic salts from historic dampness. A full moisture investigation by a CSRT surveyor, including salt analysis, is needed to confirm rising damp before DPC treatment is specified.

For failed ground floor DPM, signs include damp patches on a solid floor, damp rising at the floor/wall junction, and carpet or wood flooring moisture-damaged at the edges.

Remedial DPC Options

Where no DPC exists or the existing DPC has failed, the options are:

  1. Chemical injection DPC — proprietary silane/silicone or siloxane-based fluid injected under pressure into a course of mortar joints; creates a water-repellent band in the masonry; the most common remedial approach; BS 6576 covers installation; must be carried out by a CSRT-qualified contractor
  2. Physical DPC insertion — the wall is cut in short sections (600mm at a time) and new DPC material inserted; used for walls too narrow for injection or where structural continuity must be maintained; labour-intensive
  3. Electro-osmotic DPC — titanium anode strips installed in the wall connected to earth; attempts to reverse the electrical potential driving capillary rise; low cost but limited evidence base; not widely recommended by mainstream surveyors
  4. Drainage and ventilation — indirect approach: improving external drainage to reduce soil moisture, installing sub-floor ventilation to reduce humidity; reduces but does not eliminate rising damp

Frequently Asked Questions

Do I need a DPM in an extension with an existing damp-proof floor?

Yes. Building Regulations Part C requires a DPM in any new ground-bearing floor. Even if the existing house floor does not have a DPM (which may be the case in older properties), the extension must comply with current regulations. The extension DPM and DPC must be continuous and linked; if the existing house has no DPC at the same level, a detail connecting the extension DPM to the external wall DPC level is required.

Can I use a concrete slab without a DPM if it is thick enough?

No. Concrete alone does not act as a DPM — it is permeable to moisture vapour. A 100mm slab with no DPM will allow moisture vapour to rise and will condense under impermeable floor finishes (vinyl, ceramic tile), causing adhesive failure and floor damage. The DPM is required in addition to the slab.

What is the difference between a DPM and a vapour control layer?

A DPM (damp-proof membrane) is specifically designed to block liquid water and water vapour from the ground. A vapour control layer (VCL) is used in wall and roof construction to control vapour diffusion through the building fabric. The terminology can overlap — some DPMs can also serve as VCLs — but they are specified for different purposes and locations.

How do I fix a failed DPC in a Victorian house without disturbing the floors?

The most practical option is chemical injection through the mortar course at the appropriate level. A CSRT surveyor will specify the product and method. The injection mortar course is typically the 3rd or 4th course above floor level (minimum 150mm above finished floor). After injection, the associated plaster should be hacked off, the wall allowed to dry, and new renovating plaster applied to manage residual hygroscopic salts.

Regulations & Standards