What does Building Regulations Part H cover for foul water drainage, soakaways and septic tanks?

Quick Answer: Building Regulations Part H governs the design and installation of foul water and surface water drainage systems in England. It covers everything from the sizing of underground foul drains (minimum 100mm internal diameter for domestic use) to the design of soakaways, septic tanks, and cesspools. All new drainage installations and material alterations require building control approval, and drainage serving new dwellings must be designed to prevent surcharge or nuisance under the design storm event.

Summary

Part H of the Building Regulations is the primary technical reference for drainage work in England. It is divided into six parts: H1 (foul water drainage), H2 (wastewater treatment systems and cesspools), H3 (rainwater drainage), H4 (building over sewers), H5 (separate systems of drainage), and H6 (solid waste storage). For most tradespeople — plumbers, groundworkers, and drainage contractors — H1 and H2 are the sections that matter on a daily basis.

The hierarchy of drainage disposal is established in Part H: foul water must be directed to the public sewer where one is available and connection is reasonably practicable. Only where no public sewer connection is feasible may a private treatment system (septic tank, packaged treatment plant) or cesspool be used. Surface water should be managed through sustainable drainage (soakaway, watercourse) rather than the foul sewer wherever possible. Mixing foul and surface water in a combined sewer is only permitted where no separate system exists.

For tradespeople working on extensions, new builds, or drainage repairs, the practical implications are: minimum pipe sizes must be respected; falls must be within specified ranges to prevent blockage and self-cleansing failure; access points must be positioned at intervals that allow rodding; and any work within 3 metres of a public sewer requires notification to the sewer authority (and possibly a build-over agreement if within 3 metres of the centreline). Getting drainage wrong is expensive to fix — building control inspections at drain-laying stage are standard practice.

Key Facts

Quick Reference Table

Need to quote compliant work? squote includes relevant regulations in your quotes.

Try squote free →
Pipe Diameter Minimum Gradient Maximum Gradient Notes
75mm (branch) 1 in 20 1 in 10 WC connection minimum 100mm
100mm 1 in 80 1 in 40 (preferred) Steeper than 1:40 risks scouring
150mm 1 in 150 1 in 100 (preferred) High-flow commercial applications
225mm 1 in 300 1 in 150 Large commercial/public drains
Drainage Type Minimum Distance from Building Minimum Distance from Boundary
Soakaway 5m 5m (from adjacent property)
Septic tank 7m (recommended) Check EA guidance
Drainage field/infiltration 10m from watercourse Check EA guidance
Cesspool 7m (recommended) Check EA guidance

Detailed Guidance

Foul Water Drain Design (H1)

The design of below-ground drainage must ensure:

  1. Self-cleansing: Gradient and diameter must produce the minimum 0.75 m/s flow velocity. Drains that are too flat silt up; drains that are too steep run dry and cause sedimentation.
  2. Watertightness: All joints must be airtight and watertight. A hydraulic pressure test (water test) or pneumatic test is standard before backfilling.
  3. Structural stability: Pipes must be bedded appropriately for the depth and ground conditions. Class D bedding (selected granular fill, minimum 100mm surround) is standard for domestic work at typical depths.
  4. Access: Inspection chambers or manholes at every junction, change of direction, and at intervals not exceeding 45m.

Drain runs must be laid in straight lines between access points. Junctions should be angled in the direction of flow (oblique or curved branches, not square tees).

Inspection Chambers and Manholes

Wastewater Treatment Systems (H2)

Where a public sewer connection is not reasonably practicable, the options in order of preference are:

  1. Packaged sewage treatment plant: Produces effluent to BS EN 12566 standard; typically requires an Environment Agency (EA) registration or permit for discharge
  2. Septic tank with drainage field: Septic tanks only provide primary settlement — the effluent must then pass through a drainage field (infiltration trenches) for secondary treatment in the soil
  3. Cesspool: A sealed holding tank with no treatment — contents must be pumped out regularly; expensive to operate and only appropriate where other options are impossible

Environment Agency requirements: From January 2020, any new septic tank discharge to surface water (a ditch, stream, or river) requires an individual EA permit. The general binding rules only permit discharge to ground via a drainage field. Installers should ensure clients understand this before any system is specified.

Drainage field design: Based on percolation test results (Vp value). Total pipe length calculated from design formula in the BRE Digest 365 / Approved Document H guidance. Pipes laid at consistent depth (typically 300–700mm), in parallel runs minimum 2m apart.

Soakaway Design (H3 / Surface Water)

For surface water disposal where mains drainage is unavailable:

Building Over and Near Sewers (H4)

A public sewer is an adopted sewer maintained by the sewerage undertaker (e.g., Thames Water, Severn Trent). No structure may be built over a public sewer without consent.

Frequently Asked Questions

What is the minimum cover over a drain under a garden?

Under a garden or landscaped area, drains should have a minimum cover of 600mm to the top of the pipe (900mm in agricultural ground subject to vehicle loading). Under driveways or areas with vehicle access, minimum cover is 900mm, and concrete surround or higher-strength pipes may be required.

Can a WC be connected to a 100mm drain running at 1 in 100?

In general, no. A 100mm drain requires at minimum a gradient of 1 in 80 for acceptable self-cleansing velocity, and 1 in 40 is the preferred gradient. At 1 in 100, a 100mm drain is likely to silt and will not achieve the minimum velocity. If the site constraints force a shallower gradient, a 150mm pipe at 1 in 100 may be acceptable with high design flow.

Does a rainwater pipe need to be separate from the foul drain?

Yes — in almost all new work, surface water must be kept separate from foul drainage. Surface water should drain to soakaway, attenuation, or surface water sewer. Connecting surface water to the foul sewer is only permitted where there is no separate system available and the sewerage undertaker consents. Mixed drainage in existing combined systems may be retained, but new connections to foul sewers for surface water are not permitted without consent.

How far must a septic tank be from a house?

Approved Document H recommends a minimum 7m from any habitable building. The Environment Agency's position is similar. The drainage field must be a minimum 10m from any watercourse, and the entire system should be sited to avoid waterlogged ground. In practice, the percolation test result determines feasibility more than distance.

Who is responsible for a shared private drain?

A drain serving only one property up to the point where it joins a shared run (or the public sewer) is the responsibility of the property owner. A shared drain serving two or more properties — a "private sewer" — is the joint responsibility of all connected owners. Since October 2011, private sewers that were formerly jointly owned have been transferred to the ownership of sewerage undertakers under the Water Industry Act 1991 reforms.