Building Regs Part R: In-Building Physical Infrastructure for High-Speed Broadband in New Builds

Quick Answer: Approved Document R, Requirement R1, requires new dwellings (and buildings undergoing major renovation) in England to be built with in-building physical infrastructure capable of carrying high-speed (gigabit-ready) broadband — essentially a duct/cable route from the property boundary to a network termination point inside, plus a sensible position for the router. A later amendment, R2, requires that where a gigabit-capable network is available, the building is actually connected to it, subject to a cost cap of £2,000 per dwelling. It is a build-quality requirement checked by Building Control, not a telecoms licence matter.

Summary

Part R is the newest and smallest of the Approved Documents, but it matters because retrofitting broadband infrastructure into a finished building is expensive and disruptive. The idea is simple: build the physical pathway for fibre into the home at first fix, so a broadband operator can connect the property cheaply later without digging up driveways or chasing walls.

There are two requirements. R1 (in-building physical infrastructure) applies to new dwellings and to buildings undergoing major renovation work, and requires the ducts, conduits, and a network termination space that a gigabit-capable connection would need. R2 (connection to a gigabit-capable network) is the later upgrade: where such a network is available near the site, the developer must actually arrange the connection, up to a cost cap per dwelling. Above the cap, the developer must install infrastructure to the next-best available network instead.

For tradespeople — particularly groundworkers, electricians, and data cabling installers on new build — Part R means planning a duct route from the boundary, an entry point into the building, a draw-string or installed cabling run to a termination point, and a router position near the consumer unit with power and a clear cable route. It overlaps with structured data cabling work but is a distinct Building Regulations requirement. Get the duct in before the slab and the screed go down; chase it in afterwards and the cost multiplies.

Key Facts

Quick Reference Table

Need to quote compliant work? squote includes relevant regulations in your quotes.

Try squote free →
Item Requirement
Applies to New dwellings; buildings under major renovation; certain new non-dwellings
Transitional date Work notified on/after 26 Dec 2022
R1 In-building physical infrastructure (ducts/conduits + termination space)
R2 Connect to a gigabit network where available
Cost cap (R2) £2,000 per dwelling
"High speed" target Gigabit-ready (≥1 Gbps), typically FTTP
Major renovation trigger >25% of building envelope surface area
Router position Near consumer unit; power socket + cable route

Detailed Guidance

What "in-building physical infrastructure" actually means on site

R1 is satisfied by providing the empty pathway (and termination space) that a gigabit connection needs — you are not obliged to install the operator's fibre yourself, only to make it cheap for them to do so later. In practice that means:

  1. A duct or conduit from the property boundary (where the operator's network reaches) into the building.
  2. A clear, low-bend route from the entry point to a network termination point inside.
  3. A termination space at that point — typically a small enclosure or position near the consumer unit — where the operator's ONT/router will live.
  4. A draw cord left in the duct so a fibre can be pulled through later without re-opening the run.

The two cheap-to-get-wrong details are bend radius and burial depth. A fibre cannot negotiate sharp bends, so use sweeping bends and avoid crushed flexible conduit. External duct from the boundary must be buried at a sensible depth and capped to keep water and grit out before connection.

R2 — connection, and the cost cap

R2 goes a step further than just the pathway. Where a gigabit-capable network is available at the site, the developer must arrange for the dwelling to be connected to it. This is subject to a cost cap of £2,000 per dwelling:

"Available" is judged at the time of the work — if no gigabit network reaches the area yet, R1 (the pathway) still applies so the home is ready when one arrives.

Coordinating Part R with first fix

The cheapest time to satisfy Part R is before the floor slab, screed, and plasterboard go on:

Chasing a duct into finished blockwork and re-screeding a floor to add a missed run is exactly the cost Part R exists to avoid.

Devolution note

Part R is an England Approved Document. Wales has its own building regulations regime and its own approach to broadband infrastructure; Scotland uses the Technical Handbooks (separate standards); Northern Ireland uses its own Technical Booklets. The gigabit-ready policy direction is similar across the UK, but cite the correct national document for the project location — do not quote Approved Document R on a Scottish or Welsh job.

Frequently Asked Questions

Do I have to install the actual fibre, or just the duct?

For R1 you provide the physical infrastructure — the duct/conduit pathway, draw cord, and termination space — not the operator's fibre itself. The broadband operator pulls their fibre through later. For R2, where a gigabit network is available and within the cost cap, the dwelling must actually be connected — so the connection has to be arranged, though typically by/with the operator rather than as a cabling task for the general builder.

Does Part R apply to extensions and loft conversions?

R1 is triggered by new dwellings and by major renovation (renovation affecting more than ~25% of the building envelope). A modest extension or a loft conversion that does not cross the major-renovation threshold generally does not trigger Part R, though running a duct/data route while the walls are open is sensible. Always check the specific scope against the major-renovation definition.

What is the £2,000 cap and who pays?

The cap of £2,000 per dwelling limits how much the developer must spend to connect the dwelling to a gigabit network under R2. If connection costs more than the cap, the developer is not required to fund the gigabit connection but must still provide the gigabit-ready in-building infrastructure (R1) and connect to the best network achievable within the cap. The developer bears the cost up to the cap.

Where should the router go?

Part R expects an accessible, sensible position for the router/ONT — in practice near the electrical consumer unit, with a switched socket and a clear cable route into the living areas. Avoid a cupboard buried deep in the floor plan with no power and no onward cabling; that defeats the purpose.

Is Part R the same as needing planning permission for broadband?

No. Part R is a Building Regulations requirement enforced by Building Control as part of the build. It is separate from any planning permission and from the telecoms operators' own statutory powers to install networks. They can overlap on a site but are different regimes.

Regulations & Standards