Summary

Building control inspections are not optional extras that the building control surveyor fits in when they are passing. They are tied to legal notice requirements, and the person carrying out the work, usually the builder, is responsible for giving those notices. Miss one and the surveyor is entitled to ask you to dig out the foundation, cut back the DPC or expose the drains so they can see them. That is a cost nobody priced for.

The 2023 reforms in England added a new layer. Applications made from 1 October 2023 lapse if the work has not been "regarded as commenced" within three years of approval, and there is a separate notice to confirm the work has reached that point. Many builders still assume the old "start notice and away you go" rules apply.

This guide sets out the notices, the typical inspection stages for an extension or new build, what the surveyor checks at each one, and how to keep the job moving. It covers both local authority building control and registered building control approvers, which since April 2024 have replaced the old approved inspectors in England.

Key Facts

Quick Reference Table

Need to quote compliant work? squote includes relevant regulations in your quotes.

Try squote free →
Stage Notice required What the surveyor typically checks
Start of work At least 2 days before Approval in place, site set out, party wall matters noted
Regarded as commenced (applications from 1 Oct 2023) Within 5 days after Confirms work has reached the Regulation 46A point
Foundation excavation At least 1 day before concreting Depth, width, bearing strata, trees, drains nearby
Foundation concrete At least 1 day before covering Concrete level, steps, reinforcement if specified
Damp-proof course At least 1 day before covering DPC level at least 150 mm above ground, cavity depth below DPC, wall ties
Oversite / floor At least 1 day before covering Hardcore, DPM, insulation thickness, radon barrier where needed
Drains before backfill At least 1 day before covering Falls, bedding, pipe sizes, access points
Drains after backfill Within 5 days after Air or water test
Structural / pre-plaster As agreed with surveyor Steel beams, padstones, lintels, fire stopping, insulation
Completion Within 5 days after Fire safety, ventilation, Part L evidence, certificates

Detailed Guidance

Start notice and "commencement" are not the same thing

Since the 2023 changes in England, two separate events matter:

If the job never reaches the commenced point within three years of approval, the approval lapses and a new application is needed. This matters on jobs that are approved and then shelved.

What happens at each inspection

Foundation excavation. The surveyor checks that the trench has reached a suitable bearing stratum at the specified depth, that clay soils near trees have been dug deeper as required by the design, that the trench is clean and dry and that it is clear of existing drains. Bring the drawings and any engineer's calculations. See foundation depths and types.

Damp-proof course. They check the DPC is at least 150 mm above finished ground level, lapped and continuous, that the cavity extends below the DPC, that wall ties are correctly spaced and clean, and that cavity trays and insulation are as specified. See damp proof course.

Oversite and floor. Checks cover hardcore compaction and depth, sand blinding, the DPM and its laps and upstands, insulation type and thickness for Part L, and any radon or gas protection.

Drains. Before backfill: pipe sizes, gradients, bedding and surround, access chambers and connections. After backfill: an air or water test. Have the test kit ready on site.

Pre-plaster and structural. Most surveyors want to see steel beams, padstones, lintels and fire stopping before they disappear behind plasterboard, plus insulation in walls and roofs. Agree these visits at the start.

Completion. The surveyor checks fire safety (escape windows, smoke alarms, fire doors where needed), ventilation, stairs and guarding, energy performance evidence and, for new dwellings, the SAP calculation and air test. Have competent person certificates for electrics, gas and glazing ready.

Building notice or full plans

On a full plans application the drawings are checked in advance, and inspections confirm the work matches. On a building notice, there are no approved drawings, so the surveyor relies more heavily on site inspections and may ask for details or calculations during the job. Building notices cannot be used for some work, for example where a building over or near a public sewer is involved, or for buildings designated under the Regulatory Reform (Fire Safety) Order 2005. See building notice vs full plans application.

Booking inspections without losing days

When notice is missed

If work is covered without notice, the building control body can require it to be opened up. In practice a surveyor may accept a trial hole, a drain camera survey, or a core through the floor. Where the work cannot be verified, a completion certificate may be refused, which causes problems on a future sale and can lead to enforcement action. Contraventions of the Building Regulations are criminal offences, and the Building Safety Act 2022 increased enforcement powers.

Scotland, Wales and Northern Ireland

Frequently Asked Questions

Who is responsible for booking building control inspections?

The person carrying out the work is legally responsible for giving the notices. On most jobs that is the builder. Agree it in writing with the client so there is no confusion.

How much notice do I need to give before pouring foundations?

At least one day's notice before covering up the foundation excavation, which in practice means before concreting. Many surveyors like more notice, so book as soon as the trench is nearly ready.

What happens if I do not get a completion certificate?

The work may be treated as unapproved. It can delay or derail a house sale, insurers may query it, and the local authority can take enforcement action. Book the completion inspection promptly and supply all certificates.

Do I need building control for electrical work?

Notifiable electrical work under Part P can be self-certified by a registered competent person. If the electrician is not registered, the work must be notified to building control, who will inspect it or require an electrical installation certificate from a qualified person.

Can my approval expire?

Yes. For applications in England made from 1 October 2023, approval lapses if work is not regarded as commenced within three years. Check with the building control body before relying on an old approval.