Summary
Building control inspections are not optional extras that the building control surveyor fits in when they are passing. They are tied to legal notice requirements, and the person carrying out the work, usually the builder, is responsible for giving those notices. Miss one and the surveyor is entitled to ask you to dig out the foundation, cut back the DPC or expose the drains so they can see them. That is a cost nobody priced for.
The 2023 reforms in England added a new layer. Applications made from 1 October 2023 lapse if the work has not been "regarded as commenced" within three years of approval, and there is a separate notice to confirm the work has reached that point. Many builders still assume the old "start notice and away you go" rules apply.
This guide sets out the notices, the typical inspection stages for an extension or new build, what the surveyor checks at each one, and how to keep the job moving. It covers both local authority building control and registered building control approvers, which since April 2024 have replaced the old approved inspectors in England.
Key Facts
- Start notice — give notice at least two days before starting work (Regulation 16); some councils state two working days.
- Commencement notice (England, from 1 October 2023) — give notice not more than five days after the work is regarded as commenced under Regulation 46A.
- Lapse — approval lapses if work is not regarded as commenced within three years.
- Stage notices — at least one day's notice before covering up a foundation excavation, foundations, a damp-proof course, concrete or other material laid over the site, or any drain or sewer.
- Drain test notice — not more than five days after laying, haunching or covering a drain or sewer.
- Completion notice — not more than five days after completing the work.
- Occupation before completion — at least five days' notice before occupying a new building that is not yet complete.
- Who gives notice — the person carrying out the work, not the homeowner, unless they are doing the work themselves.
- Opening up — where notice is not given, the building control body can require work to be cut into, laid open or pulled down so it can be inspected.
- Completion certificate — issued by the building control body when satisfied; it is the evidence solicitors ask for on a sale.
- Competent person schemes — electrical, gas, heating and window work done by a registered installer is self-certified and does not need building control inspection for that element.
- Registered building control approvers — since 6 April 2024, private bodies in England must be registered with the Building Safety Regulator, and individual surveyors must be registered building inspectors.
- Higher-risk buildings — buildings at least 18 m or seven storeys with at least two residential units follow a separate gateway regime through the Building Safety Regulator.
Quick Reference Table
Need to quote compliant work? squote includes relevant regulations in your quotes.
Try squote free →| Stage | Notice required | What the surveyor typically checks |
|---|---|---|
| Start of work | At least 2 days before | Approval in place, site set out, party wall matters noted |
| Regarded as commenced (applications from 1 Oct 2023) | Within 5 days after | Confirms work has reached the Regulation 46A point |
| Foundation excavation | At least 1 day before concreting | Depth, width, bearing strata, trees, drains nearby |
| Foundation concrete | At least 1 day before covering | Concrete level, steps, reinforcement if specified |
| Damp-proof course | At least 1 day before covering | DPC level at least 150 mm above ground, cavity depth below DPC, wall ties |
| Oversite / floor | At least 1 day before covering | Hardcore, DPM, insulation thickness, radon barrier where needed |
| Drains before backfill | At least 1 day before covering | Falls, bedding, pipe sizes, access points |
| Drains after backfill | Within 5 days after | Air or water test |
| Structural / pre-plaster | As agreed with surveyor | Steel beams, padstones, lintels, fire stopping, insulation |
| Completion | Within 5 days after | Fire safety, ventilation, Part L evidence, certificates |
Detailed Guidance
Start notice and "commencement" are not the same thing
Since the 2023 changes in England, two separate events matter:
- Start of work — when you actually begin on site. You must give at least two days' notice before this.
- Regarded as commenced — a defined point under Regulation 46A. For a new building it is broadly when the foundations and lowest floor structure supporting the building are complete; Regulation 46A sets out what counts for each type of work, and your building control body will confirm which applies. You must give notice within five days of reaching it.
If the job never reaches the commenced point within three years of approval, the approval lapses and a new application is needed. This matters on jobs that are approved and then shelved.
What happens at each inspection
Foundation excavation. The surveyor checks that the trench has reached a suitable bearing stratum at the specified depth, that clay soils near trees have been dug deeper as required by the design, that the trench is clean and dry and that it is clear of existing drains. Bring the drawings and any engineer's calculations. See foundation depths and types.
Damp-proof course. They check the DPC is at least 150 mm above finished ground level, lapped and continuous, that the cavity extends below the DPC, that wall ties are correctly spaced and clean, and that cavity trays and insulation are as specified. See damp proof course.
Oversite and floor. Checks cover hardcore compaction and depth, sand blinding, the DPM and its laps and upstands, insulation type and thickness for Part L, and any radon or gas protection.
Drains. Before backfill: pipe sizes, gradients, bedding and surround, access chambers and connections. After backfill: an air or water test. Have the test kit ready on site.
Pre-plaster and structural. Most surveyors want to see steel beams, padstones, lintels and fire stopping before they disappear behind plasterboard, plus insulation in walls and roofs. Agree these visits at the start.
Completion. The surveyor checks fire safety (escape windows, smoke alarms, fire doors where needed), ventilation, stairs and guarding, energy performance evidence and, for new dwellings, the SAP calculation and air test. Have competent person certificates for electrics, gas and glazing ready.
Building notice or full plans
On a full plans application the drawings are checked in advance, and inspections confirm the work matches. On a building notice, there are no approved drawings, so the surveyor relies more heavily on site inspections and may ask for details or calculations during the job. Building notices cannot be used for some work, for example where a building over or near a public sewer is involved, or for buildings designated under the Regulatory Reform (Fire Safety) Order 2005. See building notice vs full plans application.
Booking inspections without losing days
- Ask the surveyor at the start which stages they want to see and how much notice they prefer; many offer same-day or next-day visits if booked before a cut-off time.
- Book inspections when the stage is genuinely ready. A failed visit costs a day.
- Photograph every stage with a scale (tape or level) in shot as extra evidence.
- Keep delivery tickets for concrete, insulation and steel; surveyors often ask for them.
- If the surveyor cannot attend in time, ask in writing whether you may proceed with photographic evidence. Do not cover work without that agreement.
When notice is missed
If work is covered without notice, the building control body can require it to be opened up. In practice a surveyor may accept a trial hole, a drain camera survey, or a core through the floor. Where the work cannot be verified, a completion certificate may be refused, which causes problems on a future sale and can lead to enforcement action. Contraventions of the Building Regulations are criminal offences, and the Building Safety Act 2022 increased enforcement powers.
Scotland, Wales and Northern Ireland
- Wales — the Building Regulations 2010 apply as amended in Wales, which has its own reforms; check the local authority's current notice requirements.
- Scotland — building warrants are issued under the Building (Scotland) Act 2003; the warrant comes with a Construction Compliance and Notification Plan setting out the inspection stages, and a completion certificate is submitted by the applicant.
- Northern Ireland — the Building Regulations (Northern Ireland) 2012 apply, with their own notice periods for each stage.
Frequently Asked Questions
Who is responsible for booking building control inspections?
The person carrying out the work is legally responsible for giving the notices. On most jobs that is the builder. Agree it in writing with the client so there is no confusion.
How much notice do I need to give before pouring foundations?
At least one day's notice before covering up the foundation excavation, which in practice means before concreting. Many surveyors like more notice, so book as soon as the trench is nearly ready.
What happens if I do not get a completion certificate?
The work may be treated as unapproved. It can delay or derail a house sale, insurers may query it, and the local authority can take enforcement action. Book the completion inspection promptly and supply all certificates.
Do I need building control for electrical work?
Notifiable electrical work under Part P can be self-certified by a registered competent person. If the electrician is not registered, the work must be notified to building control, who will inspect it or require an electrical installation certificate from a qualified person.
Can my approval expire?
Yes. For applications in England made from 1 October 2023, approval lapses if work is not regarded as commenced within three years. Check with the building control body before relying on an old approval.
Regulations & Standards
Building Regulations 2010 (SI 2010/2214), Regulation 16 — notices of commencement, stage notices and completion.
Building Regulations 2010, Regulation 46A — when work is regarded as commenced, inserted by the 2023 amendments in England.
Building (Approved Inspectors etc. and Review of Decisions) (England) Regulations 2023 — the new regime for registered building control approvers.
Building Safety Act 2022 — registration of building control approvers and inspectors and strengthened enforcement.
Building (Scotland) Act 2003 — building warrants and completion certificates in Scotland.
Building Regulations (Northern Ireland) 2012 — notices and inspections in Northern Ireland.
legislation.gov.uk — Building Regulations 2010, Regulation 16 — statutory notice requirements
Planning Portal — on-site approval and inspections — overview of site inspections
GOV.UK — Building regulations approval — how approval works in England and Wales
Salford City Council — commencement and building work regarded as commenced — council guidance on Regulation 46A
LABC — inspections and notices — local authority building control guidance
building control — when work needs building control at all
building notice vs full plans application — choosing the application type
completion certificates — what the certificate is and why it matters
competent person — self-certifying electrical, gas and glazing work
foundation depths and types — what the surveyor checks at foundation stage